Subject 845
Bulletin Dated: September 18, 2009
SUMMARY OF TOPICS
The following changes in requirements to the Standard for Motor Control Centers, UL 845, are being proposed for preliminary review and comment only:
1. For Preliminary Review Only: Addition of 4.2.2 to correspond with 4th edition of UL 845.
2. For Preliminary Review Only: Revision of 6.3.8 to add a blank after the word "rating."
3. For Preliminary Review Only: Revision of 6.3.50 to address Cautionary Marking Letter Size.
4. For Preliminary Review Only: Addition of 6.3.62 marking requirement.
5. For Preliminary Review Only: Revision of wording in Tables 7, 8, and 9, footnote "A."
6. For Preliminary Review Only: Revision of 8.1.7.0 and addition of 8.2.25.6 to address indirect locking schemes.
7. For Preliminary Review Only: Revision of 8.2.4.1 to correct clause references.
8. For Preliminary Review Only: Revision to 8.2.10.3 to correct clause references.
9. For Preliminary Review Only: Addition of 8.2.13.15 and 8.2.13.16 to correspond with 4th edition of UL 845.
10. For Preliminary Review Only: Revision of clauses to reference Table 17 to clarify the meaning of "ampacity."
11. For Preliminary Review Only: Addition of 8.2.20.7 (d) to be consistent with UL 891.
12. For Preliminary Review Only: Revise 8.2.26.11 to clarify spacing requirements.
13. For Preliminary Review Only: Revision of 8.2.31.3.1 to correct terminology.
14. For Preliminary Review Only: Revision of 9.3.18 temperature test requirements.
15. For Preliminary Review Only: Revision of 9.10.3.3, 9.10.10.5, and 8.3.10 to clarify requirements for doors when running a bus withstand test.
16. For Preliminary Review Only: Revision of 9.10.7 to remove "connections" from the title.
17. For Preliminary Review Only: Revise the reference in clause 9.12.1.6 to include reference to line connections.
18. For Preliminary Review Only: Revision of 9.12.6.3 and addition of 9.12.6.4 to clarify requirements for cases where the unit short-circuit rating is higher than the withstand rating of the disconnect switch
19. For Preliminary Review Only: Revision of Table 19 to add headers.
20. For Preliminary Review Only: Revision of Table 20 to correct errors.
21. For Preliminary Review Only: Revision of Table 22 to correct errors.
22. For Preliminary Review Only: Revision of Table 24 to correct subscript errors.
23. For Preliminary Review Only: Revision of Table 27 to show temperature in Kelvin (K).
24. For Preliminary Review Only: Revision of Table 27 to add superscript "m" to define the location point for the temperature rise measurement.
25. For Preliminary Review Only: Revision of Table 27 to add requirment to monitor the temperature of a bus bar at the point where it connects to a breaker.